Hard1 markMultiple Choice
PMP · Question 17 · Task 4: Empower team members
A team member complains that they are unsure what they are responsible for versus what the project manager handles. Which TWO documents/tools should the PM utilize to clarify this?
A team member complains that they are unsure what they are responsible for versus what the project manager handles. Which TWO documents/tools should the PM utilize to clarify this?
Answer options:
A.
RACI Matrix
B.
Project Schedule
C.
Team Charter
D.
Risk Register
E.
Stakeholder Register
How to approach this question
Select the tools specifically designed for role definition.
Full Answer
The RACI matrix is the standard tool for mapping tasks to roles. The Team Charter is the social contract that clarifies expectations and roles broadly.
Common mistakes
Selecting Schedule (B) or Stakeholder Register (E).
Practice the full PMP People Domain Practice Exam
60 questions · hints · full answers · grading
More questions from this exam
Q01A project manager leading a hybrid project notices that two senior engineers are constantly argui...HardQ02During a retrospective, an agile team expresses frustration that a stakeholder frequently interru...HardQ03Two team members have a fundamental disagreement about a technical approach. Both options are via...HardQ04A project manager discovers that a vendor has been contacting team members directly to offer gift...HardQ05A key stakeholder is unhappy with the project's progress and is verbally aggressive towards the p...Hard
Expert