PMP · Question 17 · Task 4: Empower team members

A team member complains that they are unsure what they are responsible for versus what the project manager handles. Which TWO documents/tools should the PM utilize to clarify this?

Answer options:

A.

RACI Matrix

B.

Project Schedule

C.

Team Charter

D.

Risk Register

E.

Stakeholder Register

How to approach this question

Select the tools specifically designed for role definition.

Full Answer

The RACI matrix is the standard tool for mapping tasks to roles. The Team Charter is the social contract that clarifies expectations and roles broadly.

Common mistakes

Selecting Schedule (B) or Stakeholder Register (E).