    Hard1 markMultiple Choice
    Task 1: Manage conflictConflict ManagementPredictive

    PMP · Question 03 · Task 1: Manage conflict

    Two team members have a fundamental disagreement about a technical approach. Both options are viable, but they have different long-term maintenance implications. The project is in the early stages, and relationships are important. Which conflict resolution technique is MOST appropriate?

    Answer options:

    A.

    Collaborate/Problem Solve

    B.

    Compromise/Reconcile

    C.

    Smooth/Accommodate

    D.

    Force/Direct

    How to approach this question

    Match the scenario characteristics (early stage, important relationships, viable options) to the definition of conflict resolution techniques.

    Full Answer

    A.Collaborate/Problem Solve✓ Correct
    Collaboration involves incorporating multiple viewpoints and insights from different perspectives. It requires a cooperative attitude and open dialogue that typically leads to consensus and commitment.

    Common mistakes

    Confusing Compromise (splitting the difference) with Collaborate (finding the best solution together).
    Question 02All questionsQuestion 04

    Practice the full PMP People Domain Practice Exam

    60 questions · hints · full answers · grading

    Sign up freeTake the exam

    More questions from this exam

    Q01A project manager leading a hybrid project notices that two senior engineers are constantly argui...HardQ02During a retrospective, an agile team expresses frustration that a stakeholder frequently interru...HardQ04A project manager discovers that a vendor has been contacting team members directly to offer gift...HardQ05A key stakeholder is unhappy with the project's progress and is verbally aggressive towards the p...HardQ06A project manager takes over a high-performing agile team. The previous PM was very directive. Th...Hard
    View all 60 questions →