PMP · Question 18 · Task 4: Empower team members
A project manager needs to make a decision about a change in the project management information system. The change affects the daily work of all team members. Which decision-making style is MOST appropriate to ensure buy-in?
A project manager needs to make a decision about a change in the project management information system. The change affects the daily work of all team members. Which decision-making style is MOST appropriate to ensure buy-in?
Answer options:
A.
Command
B.
Consultative
C.
Consensus
D.
Random/Coin Flip
How to approach this question
Match the goal (buy-in) to the style. Consensus generates the highest commitment.
Full Answer
C.Consensus✓ Correct
For decisions affecting daily work habits, Consensus is best because it ensures everyone is heard and agrees to support the outcome, reducing resistance to change.
Common mistakes
Choosing Consultative (B). While good, Consensus is better for 'buy-in'.
Practice the full PMP People Domain Practice Exam
60 questions · hints · full answers · grading
More questions from this exam
Q01A project manager leading a hybrid project notices that two senior engineers are constantly argui...HardQ02During a retrospective, an agile team expresses frustration that a stakeholder frequently interru...HardQ03Two team members have a fundamental disagreement about a technical approach. Both options are via...HardQ04A project manager discovers that a vendor has been contacting team members directly to offer gift...HardQ05A key stakeholder is unhappy with the project's progress and is verbally aggressive towards the p...Hard
Expert