PMP · Question 16 · Task 4: Empower team members
A project manager is leading a large project with multiple workstreams. The PM is overwhelmed by the volume of minor decisions required daily. What is the MOST effective way to address this?
Answer options:
Work longer hours to ensure all decisions are made correctly.
Establish clear decision-making thresholds and delegate authority to workstream leads.
Ask the sponsor to make the minor decisions.
Implement a voting system for all decisions.