Hard1 markMultiple Choice
PMP · Question 22 · Task 2: Evaluate and deliver project benefits and value
A project is using an incremental delivery approach. The first increment was released, but the stakeholders are complaining that they do not see the value yet. The project manager reviews the release and confirms it met all functional requirements.<br/><br/>What is the MOST likely cause of this issue?
A project is using an incremental delivery approach. The first increment was released, but the stakeholders are complaining that they do not see the value yet. The project manager reviews the release and confirms it met all functional requirements.<br/><br/>What is the MOST likely cause of this issue?
Answer options:
A.
The team failed to perform quality control testing.
B.
The increment delivered outputs but did not enable a complete business outcome.
C.
The stakeholders are resistant to change.
D.
The project manager did not calculate the ROI correctly.
How to approach this question
Distinguish Output vs Outcome. If it works (Output) but they don't value it, it's likely not a useful Outcome yet.
Full Answer
B.The increment delivered outputs but did not enable a complete business outcome.✓ Correct
In incremental delivery, value is only realized when a 'usable' increment is delivered. If the increment is just a technical component (Output) that doesn't allow the business to do something new or better (Outcome), stakeholders won't see value.
Common mistakes
Blaming stakeholders (C) instead of analyzing the value delivery strategy.
Practice the full PMP Business Environment Domain Practice Exam
60 questions · hints · full answers · grading
More questions from this exam
Q01A project manager is leading a medical device development project. During the execution phase, a ...HardQ02A global fintech organization is launching a new payment platform. The project manager is identif...HardQ03A project manager discovers that a subcontractor has been disposing of chemical waste improperly,...HardQ04An Agile team is developing a healthcare application. A new patient privacy regulation is passed ...HardQ05A project team is building a new headquarters. The project manager must ensure that the building ...Hard