Hard1 markMultiple Choice

PMP · Question 21 · Task 2: Evaluate and deliver project benefits and value

A project manager is creating a Benefits Management Plan. <br/><br/>Which of the following components MUST be included to ensure accountability?

Answer options:

A.

The Work Breakdown Structure (WBS)

B.

The detailed project schedule

C.

The name of the Benefit Owner

D.

The project team roster

How to approach this question

The question asks for 'Accountability'. Accountability = A Person/Owner.

Full Answer

C.The name of the Benefit Owner✓ Correct
A Benefits Management Plan must define *who* is responsible for monitoring and realizing the benefits. This is the 'Benefit Owner'. Without an owner, there is no accountability.

Common mistakes

Including project artifacts (WBS, Schedule) in the Benefits Plan.

Practice the full PMP Business Environment Domain Practice Exam

60 questions · hints · full answers · grading

More questions from this exam