    PracticePMI PMP®PMP Business Environment Domain Practice ExamQuestion 02
    Hard1 markMultiple Choice
    Task 1: Plan and manage project complianceBusiness EnvironmentComplianceTask 1

    PMP · Question 02 · Task 1: Plan and manage project compliance

    A global fintech organization is launching a new payment platform. The project manager is identifying compliance categories relevant to the project. The platform will process credit card transactions and store user personal data across servers in Europe and California.<br/><br/>Which TWO compliance categories are MOST critical for the project manager to integrate into the project management plan? (Select TWO)

    Answer options:

    A.

    Environmental regulations (e.g., ISO 14001)

    B.

    Occupational Health and Safety (OSHA)

    C.

    Data Privacy (e.g., GDPR, CCPA)

    D.

    Import/Export Trade Tariffs

    E.

    Information Security Standards (e.g., PCI-DSS)

    F.

    Labor Union Contracts

    How to approach this question

    Analyze the scenario specifics: 'Credit Card Transactions' -> PCI-DSS (Security). 'Personal Data in Europe/California' -> GDPR/CCPA (Privacy).

    Full Answer

    For a fintech payment platform, the primary compliance risks are Information Security (specifically PCI-DSS for payments) and Data Privacy (GDPR for Europe, CCPA for California). Failure in these areas represents the highest risk to the business environment.

    Common mistakes

    Selecting generic corporate compliance (OSHA, Environmental) instead of project-specific product compliance.
    Question 01All questionsQuestion 03

    Practice the full PMP Business Environment Domain Practice Exam

    60 questions · hints · full answers · grading

    Sign up freeTake the exam

    More questions from this exam

    Q01A project manager is leading a medical device development project. During the execution phase, a ...HardQ03A project manager discovers that a subcontractor has been disposing of chemical waste improperly,...HardQ04An Agile team is developing a healthcare application. A new patient privacy regulation is passed ...HardQ05A project team is building a new headquarters. The project manager must ensure that the building ...HardQ06During a compliance audit of a software project, the auditor identifies that the team is using op...Hard
    View all 60 questions →