A project team is building a new headquarters. The project manager must ensure that the building design adheres to local zoning laws regarding height and setback distances. <br/><br/>Which compliance category is PRIMARILY being addressed in this scenario?
Answer options:
Regulatory
Quality
Social
Information Security