PMP · Question 65 · Task 16: Ensure knowledge transfer for project continuity
A project manager is preparing for a planned team member transition where a senior architect will be leaving the project in three weeks. The architect has been working on critical system design components and has significant knowledge about integration requirements and technical decisions. What should the project manager do FIRST?
A project manager is preparing for a planned team member transition where a senior architect will be leaving the project in three weeks. The architect has been working on critical system design components and has significant knowledge about integration requirements and technical decisions. What should the project manager do FIRST?
Answer options:
Work with the departing architect to identify critical knowledge areas and create a structured knowledge transfer plan
Ask the architect to document all their design decisions and technical rationale
Schedule intensive training sessions between the architect and the development team
Have the architect create detailed technical specifications for all their work areas
How to approach this question
Full Answer
Common mistakes
Practice the full PMI PMP Practice Exam 6
100 questions · hints · full answers · grading