Hard1 markMultiple Choice
Task 16: Ensure knowledge transfer for project continuityknowledge transferteam transitionsarchitectural knowledgeproject continuity

PMP · Question 65 · Task 16: Ensure knowledge transfer for project continuity

A project manager is preparing for a planned team member transition where a senior architect will be leaving the project in three weeks. The architect has been working on critical system design components and has significant knowledge about integration requirements and technical decisions. What should the project manager do FIRST?

Answer options:

A.

Work with the departing architect to identify critical knowledge areas and create a structured knowledge transfer plan

B.

Ask the architect to document all their design decisions and technical rationale

C.

Schedule intensive training sessions between the architect and the development team

D.

Have the architect create detailed technical specifications for all their work areas

How to approach this question

Look for systematic approaches that identify what critical knowledge needs to be transferred and create structured plans for effective transfer.

Full Answer

A.Work with the departing architect to identify critical knowledge areas and create a structured knowledge transfer plan✓ Correct
Effective knowledge transfer for critical roles requires systematic identification of the most important knowledge areas and structured planning to ensure comprehensive and effective transfer to the right people.

Common mistakes

Relying on general documentation, assuming knowledge transfer will happen naturally through training, or not focusing on the most critical knowledge areas.

Practice the full PMI PMP Practice Exam 6

100 questions · hints · full answers · grading

More questions from this exam