Hard1 markMultiple Choice
Task 15: Manage project issuesissue managementvendor riskimpact assessmentstakeholder collaboration

PMP · Question 64 · Task 15: Manage project issues

A project manager identifies that a previously managed risk has materialized: a key vendor has announced they will discontinue support for a critical software component in six months. This is causing delays in development and concerns about long-term system sustainability. What should the project manager do FIRST?

Answer options:

A.

Update the risk register to reflect that the risk has become an issue

B.

Begin searching for alternative software components to replace the discontinued one

C.

Assess the immediate and long-term impact, then collaborate with stakeholders to determine the optimal response strategy

D.

Implement the pre-planned risk response that was developed when this risk was first identified

How to approach this question

Look for systematic approaches that assess both immediate and long-term impacts and involve stakeholders in determining the best response strategy.

Full Answer

C.Assess the immediate and long-term impact, then collaborate with stakeholders to determine the optimal response strategy✓ Correct
When risks become issues, especially those with both immediate and long-term implications, effective management requires comprehensive impact assessment and stakeholder collaboration to determine optimal response strategies.

Common mistakes

Jumping to predetermined solutions without assessing current impact, focusing on documentation before addressing the issue, or not considering both immediate and long-term implications.