PMP · Question 01 · Task 1: Manage conflict
During a sprint retrospective in an agile project, two senior developers engage in a heated argument about coding standards. The disagreement is escalating and other team members are becoming uncomfortable. What should the project manager do FIRST?
Answer options:
Immediately end the retrospective and schedule individual meetings with both developers
Facilitate a structured discussion to help both developers express their perspectives and guide the team toward consensus
Ask the Scrum Master to handle the conflict since it's occurring during a Scrum ceremony
Establish a team vote to decide which coding standard approach to adopt