Hard1 markMultiple Choice
PMP · Question 06 · Task 6: Build a team
A project manager is forming a new cross-functional team for a complex software integration project. The project requires expertise in legacy systems, modern APIs, database management, and user experience design. What should the project manager do FIRST when building this team?
A project manager is forming a new cross-functional team for a complex software integration project. The project requires expertise in legacy systems, modern APIs, database management, and user experience design. What should the project manager do FIRST when building this team?
Answer options:
A.
Request the most senior available resources from each functional area
B.
Form the team with available resources and provide training to fill skill gaps
C.
Analyze the specific technical and functional skills required and map them to available resources
D.
Create a small core team and add specialists as needed during project execution
How to approach this question
Look for systematic approaches that match team composition to project requirements. Effective team building starts with understanding what skills are needed.
Full Answer
C.Analyze the specific technical and functional skills required and map them to available resources✓ Correct
Building effective teams requires systematic analysis of project requirements and matching them to available skills. This proactive approach prevents skill gaps and ensures project success.
Common mistakes
Focusing on availability or seniority rather than specific skill requirements, or taking a reactive approach to team composition.
Practice the full PMI PMP Practice Exam 6
100 questions · hints · full answers · grading
More questions from this exam
Q01During a sprint retrospective in an agile project, two senior developers engage in a heated argum...HardQ02A project manager is leading a hybrid software development project where the client has stable re...HardQ03A team member who was previously a high performer has shown declining work quality and missed sev...HardQ04An experienced team member approaches the project manager asking for more autonomy in making tech...HardQ05A project team is transitioning from waterfall to agile methodology. Several team members express...Hard
Expert