PMP · Question 63 · Task 14: Establish project governance structure
A project manager is establishing governance for a complex international project involving multiple vendors, regulatory compliance in three countries, and integration with existing enterprise systems. The organization has standard governance structures, but this project has unique complexity and risk factors. What should the project manager do FIRST?
A project manager is establishing governance for a complex international project involving multiple vendors, regulatory compliance in three countries, and integration with existing enterprise systems. The organization has standard governance structures, but this project has unique complexity and risk factors. What should the project manager do FIRST?
Answer options:
Implement the organization's standard governance structure without modifications
Assess organizational governance and adapt it to address the project's specific international, regulatory, and integration requirements
Create entirely new governance structures designed specifically for international projects
Delegate governance establishment to the lead vendor since they have international experience