    Hard1 markMultiple Choice
    Task 8: Negotiate project agreementsnegotiationcontract managementcost analysisvendor management

    PMP · Question 08 · Task 8: Negotiate project agreements

    A project manager is negotiating a contract amendment with a vendor who is requesting a 20% price increase due to material cost inflation. The vendor is critical to project success, but the budget increase would exceed the project manager's approval authority. What should the project manager do FIRST?

    Answer options:

    A.

    Analyze the vendor's cost justification and explore alternative solutions before escalating

    B.

    Immediately escalate to the sponsor since the increase exceeds approval authority

    C.

    Reject the price increase and begin searching for alternative vendors

    D.

    Accept the price increase and adjust other project costs to compensate

    How to approach this question

    Look for approaches that demonstrate thorough preparation and analysis before negotiation or escalation. Understanding all parties' positions is crucial.

    Full Answer

    A.Analyze the vendor's cost justification and explore alternative solutions before escalating✓ Correct
    Effective negotiation requires understanding all parties' positions and constraints. Thorough analysis enables better negotiation outcomes and informed escalation when necessary.

    Common mistakes

    Immediately escalating without analysis, or making decisions that exceed authority without proper preparation.
    Question 07All questionsQuestion 09

    Practice the full PMI PMP Practice Exam 6

    100 questions · hints · full answers · grading

    Sign up freeTake the exam

    More questions from this exam

    Q01During a sprint retrospective in an agile project, two senior developers engage in a heated argum...HardQ02A project manager is leading a hybrid software development project where the client has stable re...HardQ03A team member who was previously a high performer has shown declining work quality and missed sev...HardQ04An experienced team member approaches the project manager asking for more autonomy in making tech...HardQ05A project team is transitioning from waterfall to agile methodology. Several team members express...Hard
    View all 100 questions →