For IndividualsFor Educators
ExpertMinds LogoExpertMinds
ExpertMinds

Ace your certifications with Practice Exams and AI assistance.

  • Browse Exams
  • For Educators
  • Blog
  • Privacy Policy
  • Terms of Service
  • Cookie Policy
  • Support
  • AWS SAA Exam Prep
  • PMI PMP Exam Prep
  • CPA Exam Prep
  • GCP PCA Exam Prep

© 2026 TinyHive Labs. Company number 16262776.

    PracticePMI PMP®PMI PMP Practice Exam 3Question 72
    Hard1 markMultiple Choice
    Task 4: Engage stakeholdersstakeholder disengagementstakeholder re-engagementalternative engagementstakeholder communication

    PMP · Question 72 · Task 4: Engage stakeholders

    A project manager is working on a project where a key stakeholder has been consistently absent from important meetings and unresponsive to communications. This stakeholder's input is critical for several upcoming decisions. What should the project manager do FIRST?

    Answer options:

    A.

    Reach out directly to understand the stakeholder's situation and explore alternative ways to engage them

    B.

    Escalate the stakeholder's lack of participation to their manager

    C.

    Proceed with decisions without the stakeholder's input to avoid project delays

    D.

    Find an alternative stakeholder who can provide similar input

    How to approach this question

    When key stakeholders disengage, understand the root cause and explore alternative engagement approaches before escalating or working around them.

    Full Answer

    A.Reach out directly to understand the stakeholder's situation and explore alternative ways to engage them✓ Correct
    Direct engagement to understand the stakeholder's situation often reveals barriers to participation that can be addressed through alternative engagement approaches.

    Common mistakes

    Escalating or working around the stakeholder without first attempting to understand and address the reasons for their disengagement.
    Question 71All questionsQuestion 73

    Practice the full PMI PMP Practice Exam 3

    100 questions · hints · full answers · grading

    Sign up freeTake the exam

    More questions from this exam

    Q01During a sprint retrospective in an agile project, two team members engage in a heated argument a...HardQ02A project manager is leading a hybrid software development project where the client has clearly d...HardQ03A project manager notices that a high-performing team member has become withdrawn, is frequently ...HardQ04During sprint planning for a software development project, the development team reports that they...HardQ05A project has the following earned value metrics at the end of Month 8:<br/>- Budget at Completio...Hard
    View all 100 questions →