PMP · Question 72 · Task 4: Engage stakeholders
A project manager is working on a project where a key stakeholder has been consistently absent from important meetings and unresponsive to communications. This stakeholder's input is critical for several upcoming decisions. What should the project manager do FIRST?
Answer options:
Reach out directly to understand the stakeholder's situation and explore alternative ways to engage them
Escalate the stakeholder's lack of participation to their manager
Proceed with decisions without the stakeholder's input to avoid project delays
Find an alternative stakeholder who can provide similar input
100 questions · hints · full answers · grading