For IndividualsFor Educators
ExpertMinds LogoExpertMinds
ExpertMinds

Ace your certifications with Practice Exams and AI assistance.

  • Browse Exams
  • For Educators
  • Blog
  • Privacy Policy
  • Terms of Service
  • Cookie Policy
  • Support
  • AWS SAA Exam Prep
  • PMI PMP Exam Prep
  • CPA Exam Prep
  • GCP PCA Exam Prep

© 2026 TinyHive Labs. Company number 16262776.

    PracticePMI PMP®PMI PMP Practice Exam 3Question 02
    Hard1 markMultiple Choice
    Task 13: Determine appropriate project methodology/methods and practicesmethodology selectionhybrid approachrequirements managementdelivery strategy

    PMP · Question 02 · Task 13: Determine appropriate project methodology/methods and practices

    A project manager is leading a hybrid software development project where the client has clearly defined requirements that are unlikely to change, but wants to see working software delivered every six weeks to demonstrate progress to their board of directors. Which development approach is MOST appropriate?

    Answer options:

    A.

    Pure Waterfall approach since the requirements are stable and well-defined

    B.

    Pure Agile approach to accommodate the six-week delivery cycles

    C.

    Hybrid approach combining predictive planning with iterative delivery

    D.

    Iterative approach with multiple development cycles

    How to approach this question

    Analyze the project characteristics: stable requirements suggest predictive elements, while regular delivery needs suggest iterative elements. Look for the approach that combines both.

    Full Answer

    C.Hybrid approach combining predictive planning with iterative delivery✓ Correct
    Hybrid approaches combine the best of predictive and agile methodologies. Stable requirements benefit from upfront planning, while regular demonstrations require iterative delivery.

    Common mistakes

    Choosing pure approaches when the scenario clearly shows mixed characteristics requiring different methodological elements.
    Question 01All questionsQuestion 03

    Practice the full PMI PMP Practice Exam 3

    100 questions · hints · full answers · grading

    Sign up freeTake the exam

    More questions from this exam

    Q01During a sprint retrospective in an agile project, two team members engage in a heated argument a...HardQ03A project manager notices that a high-performing team member has become withdrawn, is frequently ...HardQ04During sprint planning for a software development project, the development team reports that they...HardQ05A project has the following earned value metrics at the end of Month 8:<br/>- Budget at Completio...HardQ06A pharmaceutical project must comply with FDA regulations for clinical trial data management. Dur...Hard
    View all 100 questions →