Hard1 markShort Answer
Task 5: Plan and manage budget and resourcesearned value managementTCPI calculationcost performancebudget management
PMP · Question 69 · Task 5: Plan and manage budget and resources
A project has the following earned value data:<br/>- Budget at Completion (BAC): $500,000<br/>- Earned Value (EV): $200,000<br/>- Actual Cost (AC): $250,000<br/>- Current CPI: 0.80<br/><br/>Calculate the To-Complete Performance Index (TCPI) based on the Budget at Completion. Round to two decimal places and enter numbers only (e.g., 1.25).
A project has the following earned value data:<br/>- Budget at Completion (BAC): $500,000<br/>- Earned Value (EV): $200,000<br/>- Actual Cost (AC): $250,000<br/>- Current CPI: 0.80<br/><br/>Calculate the To-Complete Performance Index (TCPI) based on the Budget at Completion. Round to two decimal places and enter numbers only (e.g., 1.25).
How to approach this question
Use the TCPI formula: TCPI = (BAC - EV) / (BAC - AC). Substitute the values and calculate to two decimal places.
Full Answer
TCPI = (BAC - EV) / (BAC - AC) = ($500,000 - $200,000) / ($500,000 - $250,000) = $300,000 / $250,000 = 1.20
Common mistakes
Using the wrong TCPI formula or confusing it with other earned value calculations like CPI or EAC formulas.
Practice the full PMI PMP Practice Exam 3
100 questions · hints · full answers · grading
More questions from this exam
Q01During a sprint retrospective in an agile project, two team members engage in a heated argument a...HardQ02A project manager is leading a hybrid software development project where the client has clearly d...HardQ03A project manager notices that a high-performing team member has become withdrawn, is frequently ...HardQ04During sprint planning for a software development project, the development team reports that they...HardQ05A project has the following earned value metrics at the end of Month 8:<br/>- Budget at Completio...Hard
Expert