    PracticePMI PMP®PMI PMP Practice Exam 3Question 67
    Hard1 markMultiple Choice
    Task 13: Mentor relevant stakeholdersindividual developmentcommunication skillsservant leadershipteam member coaching

    PMP · Question 67 · Task 13: Mentor relevant stakeholders

    A project manager is leading a team where one member consistently produces excellent technical work but has difficulty communicating with other team members and stakeholders. This is starting to affect team collaboration and stakeholder relationships. What should the project manager do?

    Answer options:

    A.

    Provide coaching and support to help the team member develop communication skills while leveraging their technical strengths

    B.

    Assign the team member to work independently on technical tasks to minimize communication requirements

    C.

    Pair the team member with someone who has strong communication skills

    D.

    Focus on the team member's technical contributions and accept the communication limitations

    How to approach this question

    Servant leadership focuses on developing team members' capabilities while leveraging their strengths, rather than working around their limitations.

    Full Answer

    A.Provide coaching and support to help the team member develop communication skills while leveraging their technical strengths✓ Correct
    Servant leaders focus on developing team members' capabilities. Providing coaching and support helps the individual grow while maintaining their valuable technical contributions.

    Common mistakes

    Working around the communication limitations instead of helping the team member develop these important skills for their growth and team effectiveness.
    Question 66All questionsQuestion 68

    Practice the full PMI PMP Practice Exam 3

    100 questions · hints · full answers · grading

    Sign up freeTake the exam

    More questions from this exam

    Q01During a sprint retrospective in an agile project, two team members engage in a heated argument a...HardQ02A project manager is leading a hybrid software development project where the client has clearly d...HardQ03A project manager notices that a high-performing team member has become withdrawn, is frequently ...HardQ04During sprint planning for a software development project, the development team reports that they...HardQ05A project has the following earned value metrics at the end of Month 8:<br/>- Budget at Completio...Hard