PMP · Question 62 · Task 9: Integrate project planning activities
A project manager discovers that two different teams working on related project components have developed incompatible technical approaches. The incompatibility wasn't discovered until integration testing began. What should the project manager do FIRST?
Answer options:
Determine which team's approach is technically superior and require the other team to adapt
Require both teams to start over with a coordinated approach
Assess the impact of the incompatibility and evaluate options for resolution, including technical and schedule implications
Escalate the technical incompatibility to senior management for resolution
100 questions · hints · full answers · grading