    PracticePMI PMP®PMI PMP Practice Exam 3Question 55
    Hard1 markMultiple Choice
    Task 1: Plan and manage project compliancecompliance requirementsgovernment contractsagile adaptationprocess integration

    PMP · Question 55 · Task 1: Plan and manage project compliance

    A project manager is working on a government contract that requires specific documentation and approval processes. The project team, which is experienced with agile methods, is frustrated with what they perceive as bureaucratic overhead. What should the project manager do to address this tension?

    Answer options:

    A.

    Minimize the documentation requirements to maintain team agility

    B.

    Help the team understand the compliance requirements and find ways to integrate them efficiently with agile practices

    C.

    Explain to the team that government contracts require different approaches than commercial projects

    D.

    Assign specific team members to handle all compliance-related activities

    How to approach this question

    When teams face compliance requirements that conflict with their preferred practices, help them understand the requirements and find efficient ways to integrate them.

    Full Answer

    B.Help the team understand the compliance requirements and find ways to integrate them efficiently with agile practices✓ Correct
    Understanding compliance requirements and finding efficient integration approaches helps teams maintain effectiveness while meeting necessary regulatory obligations.

    Common mistakes

    Either dismissing compliance requirements or accepting inefficiency, instead of helping teams find ways to integrate requirements effectively.
    Question 54All questionsQuestion 56

    Practice the full PMI PMP Practice Exam 3

    100 questions · hints · full answers · grading

    Sign up freeTake the exam

    More questions from this exam

    Q01During a sprint retrospective in an agile project, two team members engage in a heated argument a...HardQ02A project manager is leading a hybrid software development project where the client has clearly d...HardQ03A project manager notices that a high-performing team member has become withdrawn, is frequently ...HardQ04During sprint planning for a software development project, the development team reports that they...HardQ05A project has the following earned value metrics at the end of Month 8:<br/>- Budget at Completio...Hard