Hard1 markMultiple Choice
Task 2: Evaluate and deliver project benefits and valuestakeholder satisfactionbusiness valuestakeholder engagementvalue perception
PMP · Question 36 · Task 2: Evaluate and deliver project benefits and value
A project manager discovers that the project's key performance indicators show the team is meeting all technical milestones, but stakeholder satisfaction surveys indicate declining confidence in the project's ability to deliver business value. What should the project manager do FIRST?
A project manager discovers that the project's key performance indicators show the team is meeting all technical milestones, but stakeholder satisfaction surveys indicate declining confidence in the project's ability to deliver business value. What should the project manager do FIRST?
Answer options:
A.
Engage with stakeholders to understand the disconnect between technical progress and perceived business value
B.
Increase communication frequency to better inform stakeholders about technical progress
C.
Review the project scope to ensure alignment with business objectives
D.
Accelerate delivery to demonstrate business value sooner
How to approach this question
When there's a disconnect between project metrics and stakeholder perception, understand the stakeholder perspective first before taking corrective action.
Full Answer
A.Engage with stakeholders to understand the disconnect between technical progress and perceived business value✓ Correct
Stakeholder engagement to understand their concerns provides the insight needed to address the disconnect between technical progress and perceived value.
Common mistakes
Assuming more communication or faster delivery will solve perception issues without understanding what's driving the stakeholder concerns.
Practice the full PMI PMP Practice Exam 3
100 questions · hints · full answers · grading
More questions from this exam
Q01During a sprint retrospective in an agile project, two team members engage in a heated argument a...HardQ02A project manager is leading a hybrid software development project where the client has clearly d...HardQ03A project manager notices that a high-performing team member has become withdrawn, is frequently ...HardQ04During sprint planning for a software development project, the development team reports that they...HardQ05A project has the following earned value metrics at the end of Month 8:<br/>- Budget at Completio...Hard
Expert