    PracticePMI PMP®PMI PMP Mini Practice ExamQuestion 011
    Hard1 markMultiple Choice
    Task 1: Plan and manage project complianceBusiness EnvironmentCompliance

    PMP · Question 011 · Task 1: Plan and manage project compliance

    During the execution of a project, a new regulation is passed that impacts the project's compliance requirements. The project is 80% complete. What should the project manager do FIRST?

    Answer options:

    A.

    Continue with the current plan as the law was passed after the project started.

    B.

    Assess the impact of the new regulation on the project scope and deliverables.

    C.

    Immediately implement the necessary changes to ensure compliance.

    D.

    Close the project and start a new one to address the compliance needs.

    How to approach this question

    New Regulation -> Assess Impact -> Plan Response.

    Full Answer

    B.Assess the impact of the new regulation on the project scope and deliverables.✓ Correct
    Business Environment Task 1 focuses on compliance. When the environment changes (Task 3), the PM must assess the impact on scope before taking action.

    Common mistakes

    Choosing A (Ignoring law) or C (Acting without planning).
    Question 010All questionsQuestion 012

    Practice the full PMI PMP Mini Practice Exam

    20 questions · hints · full answers · grading

    Sign up freeTake the exam

    More questions from this exam

    Q001A project manager is leading a hybrid project. During a sprint review, a key stakeholder angrily ...HardQ002A high-performing team member on an agile team has recently become withdrawn and is missing daily...HardQ003A project manager is taking over a project where the team is demotivated due to micromanagement b...HardQ004A project team is distributed across three different time zones. Communication has been disjointe...HardQ005During a project negotiation with a vendor, the vendor states they cannot meet the required deliv...Hard
    View all 20 questions →