Hard1 markMultiple Choice
PMP · Question 010 · Task 13: Determine appropriate project methodology
A project manager is assigned to a project with a high degree of uncertainty regarding requirements. The organization traditionally uses predictive methods, but the sponsor is open to new approaches. Which methodology is MOST appropriate for this scenario?
A project manager is assigned to a project with a high degree of uncertainty regarding requirements. The organization traditionally uses predictive methods, but the sponsor is open to new approaches. Which methodology is MOST appropriate for this scenario?
Answer options:
A.
Predictive
B.
Agile
C.
Waterfall
D.
Phased-Gate
How to approach this question
Match 'High Uncertainty' to 'Agile'.
Full Answer
B.Agile✓ Correct
Task 13 requires determining the methodology. High uncertainty and undefined requirements are the primary indicators for selecting an Agile/Adaptive approach.
Common mistakes
Choosing A because the organization is traditional (Methodology should fit the project, not just history).
Practice the full PMI PMP Mini Practice Exam
20 questions · hints · full answers · grading
More questions from this exam
Q001A project manager is leading a hybrid project. During a sprint review, a key stakeholder angrily ...HardQ002A high-performing team member on an agile team has recently become withdrawn and is missing daily...HardQ003A project manager is taking over a project where the team is demotivated due to micromanagement b...HardQ004A project team is distributed across three different time zones. Communication has been disjointe...HardQ005During a project negotiation with a vendor, the vendor states they cannot meet the required deliv...Hard
Expert