For IndividualsFor Educators
ExpertMinds LogoExpertMinds
ExpertMinds

Ace your certifications with Practice Exams and AI assistance.

  • Browse Exams
  • For Educators
  • Blog
  • Privacy Policy
  • Terms of Service
  • Cookie Policy
  • Support
  • AWS SAA Exam Prep
  • PMI PMP Exam Prep
  • CPA Exam Prep
  • GCP PCA Exam Prep

© 2026 TinyHive Labs. Company number 16262776.

    PracticePMI PMP®PMI PMP Mini Practice ExamQuestion 012
    Hard1 markMultiple Choice
    Task 3: Assess and manage risksProcessRisk

    PMP · Question 012 · Task 3: Assess and manage risks

    A project manager is creating a risk management plan for a complex infrastructure project. The sponsor asks why the project manager is spending so much time on this when the project hasn't even started execution. What is the BEST response?

    Answer options:

    A.

    Risk management is a mandatory requirement of the PMBOK Guide.

    B.

    It is necessary to identify all risks before execution begins.

    C.

    Early risk planning minimizes the impact of threats and maximizes opportunities, protecting project value.

    D.

    The insurance company requires a detailed risk register for coverage.

    How to approach this question

    Choose the answer that links the process to Business Value.

    Full Answer

    C.Early risk planning minimizes the impact of threats and maximizes opportunities, protecting project value.✓ Correct
    The PM must justify processes by linking them to value delivery. Risk management is about increasing the probability of success (Value).

    Common mistakes

    Choosing A (Dogmatic) or B (Technically incorrect - risk is iterative).
    Question 011All questionsQuestion 013

    Practice the full PMI PMP Mini Practice Exam

    20 questions · hints · full answers · grading

    Sign up freeTake the exam

    More questions from this exam

    Q001A project manager is leading a hybrid project. During a sprint review, a key stakeholder angrily ...HardQ002A high-performing team member on an agile team has recently become withdrawn and is missing daily...HardQ003A project manager is taking over a project where the team is demotivated due to micromanagement b...HardQ004A project team is distributed across three different time zones. Communication has been disjointe...HardQ005During a project negotiation with a vendor, the vendor states they cannot meet the required deliv...Hard
    View all 20 questions →