PMP · Question 26 · Task 7: Plan and manage quality of products/deliverables
An agile team delivers a feature that meets all acceptance criteria, but the code is messy and lacks comments, making future maintenance difficult. Which quality standard was missed?
Answer options:
Acceptance Criteria
Definition of Ready
Definition of Done
Product Roadmap