PMP · Question 25 · Task 7: Plan and manage quality of products/deliverables
Which of the following are costs of conformance (money spent to avoid failures)? (Select TWO)
Answer options:
Training
Warranty work
Testing/Inspection
Rework
Scrap
Liability claims