PMP · Question 04 · Task 1: Execute project with the urgency required to deliver business value
A project manager is leading a team to develop a new mobile application. The market is highly volatile. The sponsor wants to ensure the team delivers the highest value features first. Which artifact should the project manager primarily rely on to facilitate this?
A project manager is leading a team to develop a new mobile application. The market is highly volatile. The sponsor wants to ensure the team delivers the highest value features first. Which artifact should the project manager primarily rely on to facilitate this?
Answer options:
A.
The Project Charter
B.
The Product Backlog
C.
The Work Breakdown Structure (WBS)
D.
The Benefits Management Plan
How to approach this question
Associate 'highest value features first' and 'volatile market' with Agile/Adaptive artifacts.
Full Answer
B.The Product Backlog✓ Correct
In an agile/adaptive context (implied by 'volatile market'), the Product Backlog is the tool used to subdivide tasks and prioritize them to deliver value incrementally.
Common mistakes
Confusing the strategic Benefits Management Plan with the tactical Product Backlog.
Practice the full PMP Process Domain Practice Exam
60 questions · hints · full answers · grading
More questions from this exam
Q01A project team is developing a new financial software product using an agile approach. The produc...HardQ02A hybrid project is developing a new smart home device. The hardware component follows a predicti...HardQ03During a predictive construction project, the client requests a change to the interior design mat...HardQ05A global project team is facing difficulties with communication due to time zone differences. Cri...HardQ06A project manager takes over a project that is halfway through execution. Stakeholders are compla...Hard
Expert