Hard1 markMultiple Choice

PMP · Question 04 · Task 1: Execute project with the urgency required to deliver business value

A project manager is leading a team to develop a new mobile application. The market is highly volatile. The sponsor wants to ensure the team delivers the highest value features first. Which artifact should the project manager primarily rely on to facilitate this?

Answer options:

A.

The Project Charter

B.

The Product Backlog

C.

The Work Breakdown Structure (WBS)

D.

The Benefits Management Plan

How to approach this question

Associate 'highest value features first' and 'volatile market' with Agile/Adaptive artifacts.

Full Answer

B.The Product Backlog✓ Correct
In an agile/adaptive context (implied by 'volatile market'), the Product Backlog is the tool used to subdivide tasks and prioritize them to deliver value incrementally.

Common mistakes

Confusing the strategic Benefits Management Plan with the tactical Product Backlog.