Hard1 markMultiple Choice
PMP · Question 27 · Task 8: Plan and manage scope
A stakeholder directly asks a team member to add a small feature. The team member adds it because it only takes 2 hours. This is an example of:
A stakeholder directly asks a team member to add a small feature. The team member adds it because it only takes 2 hours. This is an example of:
Answer options:
A.
Progressive Elaboration
B.
Scope Creep
C.
Gold Plating
D.
Agile Adaptation
How to approach this question
Identify uncontrolled change. Differentiate Creep (requested) vs Gold Plating (volunteered).
Full Answer
B.Scope Creep✓ Correct
Scope creep occurs when scope changes bypass the formal change control process. Even small changes accumulate.
Common mistakes
Confusing Scope Creep with Gold Plating (Gold plating originates from the team wanting to impress, Creep usually originates from outside requests bypassing process).
Practice the full PMP Process Domain Practice Exam
60 questions · hints · full answers · grading
More questions from this exam
Q01A project team is developing a new financial software product using an agile approach. The produc...HardQ02A hybrid project is developing a new smart home device. The hardware component follows a predicti...HardQ03During a predictive construction project, the client requests a change to the interior design mat...HardQ04A project manager is leading a team to develop a new mobile application. The market is highly vol...HardQ05A global project team is facing difficulties with communication due to time zone differences. Cri...Hard
Expert