Hard1 markMultiple Choice
PMP · Question 34 · Task 8: Negotiate project agreements
An agile team is struggling to reach an agreement on the Definition of Done (DoD). The testers want strict criteria, while developers argue it will slow them down. How should the PM facilitate this negotiation?
An agile team is struggling to reach an agreement on the Definition of Done (DoD). The testers want strict criteria, while developers argue it will slow them down. How should the PM facilitate this negotiation?
Answer options:
A.
Decide the DoD for them based on industry standards.
B.
Side with the testers to ensure quality.
C.
Facilitate a session to visualize the cost of technical debt vs. velocity, helping them find a balance they can commit to.
D.
Let them operate without a DoD until they agree.
How to approach this question
The PM is a facilitator. Help the parties see the 'Why' to reach agreement.
Full Answer
C.Facilitate a session to visualize the cost of technical debt vs. velocity, helping them find a balance they can commit to.✓ Correct
Negotiating internal agreements requires helping parties understand the consequences of their positions. Visualizing technical debt helps developers see the value of stricter criteria, leading to a shared agreement.
Common mistakes
Making the decision for them (A).
Practice the full PMP People Domain Practice Exam
60 questions · hints · full answers · grading
More questions from this exam
Q01A project manager leading a hybrid project notices that two senior engineers are constantly argui...HardQ02During a retrospective, an agile team expresses frustration that a stakeholder frequently interru...HardQ03Two team members have a fundamental disagreement about a technical approach. Both options are via...HardQ04A project manager discovers that a vendor has been contacting team members directly to offer gift...HardQ05A key stakeholder is unhappy with the project's progress and is verbally aggressive towards the p...Hard
Expert