Hard1 markMultiple Choice
PMP · Question 33 · Task 8: Negotiate project agreements
A project manager is negotiating a service level agreement (SLA) with a vendor. The vendor is insisting on a price that is 10% over budget. The PM knows the vendor wants to enter this new market segment. What is the BEST negotiation strategy?
A project manager is negotiating a service level agreement (SLA) with a vendor. The vendor is insisting on a price that is 10% over budget. The PM knows the vendor wants to enter this new market segment. What is the BEST negotiation strategy?
Answer options:
A.
Demand the price be lowered or threaten to cancel.
B.
Focus on the vendor's interest in market entry and offer a case study/testimonial in exchange for the lower price.
C.
Split the difference (pay 5% over budget).
D.
Accept the higher price and cut scope elsewhere.
How to approach this question
Look for the 'Win-Win' option that addresses the other party's underlying interests.
Full Answer
B.Focus on the vendor's interest in market entry and offer a case study/testimonial in exchange for the lower price.✓ Correct
Effective negotiation involves identifying shared interests. The vendor wants market entry (marketing value); the PM wants a lower price. Trading these creates value for both sides.
Common mistakes
Thinking negotiation is a zero-sum game (A or C).
Practice the full PMP People Domain Practice Exam
60 questions · hints · full answers · grading
More questions from this exam
Q01A project manager leading a hybrid project notices that two senior engineers are constantly argui...HardQ02During a retrospective, an agile team expresses frustration that a stakeholder frequently interru...HardQ03Two team members have a fundamental disagreement about a technical approach. Both options are via...HardQ04A project manager discovers that a vendor has been contacting team members directly to offer gift...HardQ05A key stakeholder is unhappy with the project's progress and is verbally aggressive towards the p...Hard
Expert