Hard1 markMultiple Choice
PMP · Question 27 · Task 6: Build a team
A key technical lead is leaving the project in two weeks. The project is halfway through. Which TWO actions should the PM take to ensure knowledge transfer?
A key technical lead is leaving the project in two weeks. The project is halfway through. Which TWO actions should the PM take to ensure knowledge transfer?
Answer options:
A.
Ask the lead to write a comprehensive manual of everything they know.
B.
Facilitate knowledge sharing sessions (e.g., brown bag, shadowing) with the remaining team members.
C.
Pair the departing lead with a successor for the remaining time.
D.
Cancel the lead's remaining tasks so they can relax.
E.
Record the lead performing their daily tasks.
How to approach this question
Select active, interactive methods of knowledge transfer.
Full Answer
Pairing and interactive sessions allow for the transfer of tacit knowledge (experience/intuition) which is hard to document. This is more effective than writing documentation alone.
Common mistakes
Relying on documentation (A).
Practice the full PMP People Domain Practice Exam
60 questions · hints · full answers · grading
More questions from this exam
Q01A project manager leading a hybrid project notices that two senior engineers are constantly argui...HardQ02During a retrospective, an agile team expresses frustration that a stakeholder frequently interru...HardQ03Two team members have a fundamental disagreement about a technical approach. Both options are via...HardQ04A project manager discovers that a vendor has been contacting team members directly to offer gift...HardQ05A key stakeholder is unhappy with the project's progress and is verbally aggressive towards the p...Hard
Expert