Hard1 markMultiple Choice
PMP · Question 26 · Task 6: Build a team
A team has been working together for six months. They trust each other, adjust their work habits to support one another, and require minimal supervision from the PM. Which Tuckman stage are they in?
A team has been working together for six months. They trust each other, adjust their work habits to support one another, and require minimal supervision from the PM. Which Tuckman stage are they in?
Answer options:
A.
Forming
B.
Storming
C.
Norming
D.
Performing
How to approach this question
Match the description (autonomy, trust, high output) to the stage.
Full Answer
D.Performing✓ Correct
Performing is characterized by high autonomy and synergy. The team solves problems without the leader's intervention.
Common mistakes
Confusing Norming (getting along) with Performing (excelling/autonomous).
Practice the full PMP People Domain Practice Exam
60 questions · hints · full answers · grading
More questions from this exam
Q01A project manager leading a hybrid project notices that two senior engineers are constantly argui...HardQ02During a retrospective, an agile team expresses frustration that a stakeholder frequently interru...HardQ03Two team members have a fundamental disagreement about a technical approach. Both options are via...HardQ04A project manager discovers that a vendor has been contacting team members directly to offer gift...HardQ05A key stakeholder is unhappy with the project's progress and is verbally aggressive towards the p...Hard
Expert