PMP · Question 16 · Task 2: Evaluate and deliver project benefits and value
A project delivers a new CRM software (Output). The sales team uses the software to track leads more effectively (Outcome). As a result, revenue increases by 15% (Benefit).<br/><br/>Which of these should the project manager PRIMARILY track to demonstrate the project's success to the business stakeholders?
Answer options:
The successful installation of the CRM software
The number of sales team members trained
The increase in revenue
The completion of the project on time and on budget