Hard1 markMultiple Choice
PMP · Question 15 · Task 1: Plan and manage project compliance
A project manager is classifying potential threats to compliance for a construction project in a historic city center. <br/><br/>Which TWO scenarios represent 'Environmental' compliance threats? (Select TWO)
A project manager is classifying potential threats to compliance for a construction project in a historic city center. <br/><br/>Which TWO scenarios represent 'Environmental' compliance threats? (Select TWO)
Answer options:
A.
Failure to pay overtime wages to construction workers
B.
Discovering archaeological artifacts during excavation
C.
Using software that has not been security patched
D.
Exceeding the budget for raw materials
E.
Noise levels exceeding city decibel limits during night shifts
F.
Lack of wheelchair ramps in the final design
How to approach this question
Identify issues related to the physical surroundings (Noise, Artifacts/Land).
Full Answer
Environmental compliance covers impacts on the physical environment and community well-being. Noise pollution (E) and disturbing archaeological heritage (B) fall under environmental protection regulations in many jurisdictions. Wages (A) are labor law. Ramps (F) are accessibility.
Common mistakes
Thinking Environmental only means 'nature/trees'. It includes noise, dust, and heritage.
Practice the full PMP Business Environment Domain Practice Exam
60 questions · hints · full answers · grading
More questions from this exam
Q01A project manager is leading a medical device development project. During the execution phase, a ...HardQ02A global fintech organization is launching a new payment platform. The project manager is identif...HardQ03A project manager discovers that a subcontractor has been disposing of chemical waste improperly,...HardQ04An Agile team is developing a healthcare application. A new patient privacy regulation is passed ...HardQ05A project team is building a new headquarters. The project manager must ensure that the building ...Hard
Expert