PMP · Question 83 · Task 1: Plan and manage project compliance
A project manager is reviewing the lessons learned from a previous project. They see that the previous project failed because the team did not understand the compliance requirements. What should the PM do for the new project?
Answer options:
Copy the compliance plan from the old project.
Identify compliance requirements early, involve compliance experts in the planning phase, and schedule regular compliance reviews.
Ignore it; this team is smarter.
Assign the compliance risk to a vendor.