Hard1 markMultiple Choice
Task 9: Collaborate with stakeholdersPeopleStakeholdersPolitics

PMP · Question 82 · Task 9: Collaborate with stakeholders

A project manager is leading a project to implement a new ERP system. The project affects the Finance, HR, and Sales departments. The Finance Director is the Sponsor. The HR Director is resisting the change. The Sales Director is neutral. Who is the most critical stakeholder to manage to resolve the resistance?

Answer options:

A.

The Sales Director

B.

The HR Director

C.

The Finance Director (Sponsor)

D.

The Project Team

How to approach this question

Political Awareness. Peer-to-Peer influence.

Full Answer

C.The Finance Director (Sponsor)✓ Correct
Task 9 (Collaborate) and Task 4 (Stakeholders). When facing executive resistance, the PM often needs to leverage the Sponsor's political capital.

Common mistakes

Trying to fight a Director alone.

Practice the full PMI PMP Practice Exam

114 questions · hints · full answers · grading