Hard1 markMultiple Choice
PMP · Question 82 · Task 9: Collaborate with stakeholders
A project manager is leading a project to implement a new ERP system. The project affects the Finance, HR, and Sales departments. The Finance Director is the Sponsor. The HR Director is resisting the change. The Sales Director is neutral. Who is the most critical stakeholder to manage to resolve the resistance?
A project manager is leading a project to implement a new ERP system. The project affects the Finance, HR, and Sales departments. The Finance Director is the Sponsor. The HR Director is resisting the change. The Sales Director is neutral. Who is the most critical stakeholder to manage to resolve the resistance?
Answer options:
A.
The Sales Director
B.
The HR Director
C.
The Finance Director (Sponsor)
D.
The Project Team
How to approach this question
Political Awareness. Peer-to-Peer influence.
Full Answer
C.The Finance Director (Sponsor)✓ Correct
Task 9 (Collaborate) and Task 4 (Stakeholders). When facing executive resistance, the PM often needs to leverage the Sponsor's political capital.
Common mistakes
Trying to fight a Director alone.
Practice the full PMI PMP Practice Exam
114 questions · hints · full answers · grading
More questions from this exam
Q01During a daily standup in a hybrid project, two senior developers begin arguing about the archite...HardQ02A project manager takes over a project where the team is demoralized. The previous PM was authori...HardQ03A key stakeholder is unhappy with the product increment delivered in the last sprint, claiming it...HardQ04A project team in a matrix organization is struggling. The functional manager keeps pulling key r...HardQ05A project manager is leading a virtual team spread across four time zones. Team members report fe...Hard
Expert