Medium1 markMultiple Choice
PMP · Question 84 · Task 14: Establish project governance structure
A project manager is leading a project to develop a new drug. The project is in Phase 2 (Clinical Trials). The results of the first trial are inconclusive. The governance board requires a 'Kill Point' review. What is the likely outcome?
A project manager is leading a project to develop a new drug. The project is in Phase 2 (Clinical Trials). The results of the first trial are inconclusive. The governance board requires a 'Kill Point' review. What is the likely outcome?
Answer options:
A.
The project will be cancelled immediately.
B.
The project will proceed to Phase 3 automatically.
C.
The board will review the data and decide to either: Continue, Cancel, or request Rework/Additional Trials.
D.
The PM will be fired.
How to approach this question
Phase Gate = Go/No-Go Decision.
Full Answer
C.The board will review the data and decide to either: Continue, Cancel, or request Rework/Additional Trials.✓ Correct
Task 14 (Governance). Phase gates ensure the project is still viable before investing more money. Inconclusive data usually triggers a 'Rework' or 'More Info' decision, not automatic kill or go.
Common mistakes
Thinking Kill Point means automatic death.
Practice the full PMI PMP Practice Exam
114 questions · hints · full answers · grading
More questions from this exam
Q01During a daily standup in a hybrid project, two senior developers begin arguing about the archite...HardQ02A project manager takes over a project where the team is demoralized. The previous PM was authori...HardQ03A key stakeholder is unhappy with the product increment delivered in the last sprint, claiming it...HardQ04A project team in a matrix organization is struggling. The functional manager keeps pulling key r...HardQ05A project manager is leading a virtual team spread across four time zones. Team members report fe...Hard
Expert