Hard1 markMultiple Choice
PMP · Question 20 · Task 2: Lead a team
A project manager observes that the team is struggling to reach consensus on technical decisions, leading to long meetings and delays. The team is in the 'Storming' phase. Which leadership style is MOST appropriate?
A project manager observes that the team is struggling to reach consensus on technical decisions, leading to long meetings and delays. The team is in the 'Storming' phase. Which leadership style is MOST appropriate?
Answer options:
A.
Delegating - Let the team figure it out to build self-reliance.
B.
Coaching/Facilitating - Guide the team through the conflict resolution process.
C.
Directing - Make the decisions for them to save time.
D.
Supporting - Step back and only intervene if asked.
How to approach this question
Match Leadership Style (Situational Leadership) to Team Phase. Storming -> Coaching.
Full Answer
B.Coaching/Facilitating - Guide the team through the conflict resolution process.✓ Correct
Tuckman's Ladder: Storming is characterized by conflict. The leader must facilitate resolution and establish norms (Coaching) to help them reach Norming.
Common mistakes
Thinking 'Agile' always means Delegating. You only delegate to a Performing team.
Practice the full PMI PMP Practice Exam
114 questions · hints · full answers · grading
More questions from this exam
Q01During a daily standup in a hybrid project, two senior developers begin arguing about the archite...HardQ02A project manager takes over a project where the team is demoralized. The previous PM was authori...HardQ03A key stakeholder is unhappy with the product increment delivered in the last sprint, claiming it...HardQ04A project team in a matrix organization is struggling. The functional manager keeps pulling key r...HardQ05A project manager is leading a virtual team spread across four time zones. Team members report fe...Hard
Expert