For IndividualsFor Educators
ExpertMinds LogoExpertMinds
ExpertMinds

Ace your certifications with Practice Exams and AI assistance.

  • Browse Exams
  • For Educators
  • Blog
  • Privacy Policy
  • Terms of Service
  • Cookie Policy
  • Support
  • AWS SAA Exam Prep
  • PMI PMP Exam Prep
  • CPA Exam Prep
  • GCP PCA Exam Prep

© 2026 TinyHive Labs. Company number 16262776.

    PracticePMI PMP®PMI PMP Practice ExamQuestion 19
    Hard1 markMultiple Choice
    Task 17: Plan and manage project closureProcessClosure

    PMP · Question 19 · Task 17: Plan and manage project closure

    A project manager is closing a project. The deliverables have been accepted, and the final report is written. Which TWO activities must still be completed to officially close the project?

    Answer options:

    A.

    Release project resources

    B.

    Validate scope

    C.

    Calculate the final CPI

    D.

    Archive project documents and update the lessons learned repository

    E.

    Conduct the kick-off meeting

    F.

    Perform qualitative risk analysis

    How to approach this question

    Select TWO. Think: What happens at the very end? Releasing people and saving data.

    Full Answer

    Project Closure (Task 17) involves administrative closure (archiving, lessons learned) and resource release.

    Common mistakes

    Confusing 'Validate Scope' (Client Acceptance) with Closure. Acceptance is an input to closure.
    Question 18All questionsQuestion 20

    Practice the full PMI PMP Practice Exam

    114 questions · hints · full answers · grading

    Sign up freeTake the exam

    More questions from this exam

    Q01During a daily standup in a hybrid project, two senior developers begin arguing about the archite...HardQ02A project manager takes over a project where the team is demoralized. The previous PM was authori...HardQ03A key stakeholder is unhappy with the product increment delivered in the last sprint, claiming it...HardQ04A project team in a matrix organization is struggling. The functional manager keeps pulling key r...HardQ05A project manager is leading a virtual team spread across four time zones. Team members report fe...Hard
    View all 114 questions →