PMP · Question 19 · Task 17: Plan and manage project closure
A project manager is closing a project. The deliverables have been accepted, and the final report is written. Which TWO activities must still be completed to officially close the project?
Answer options:
Release project resources
Validate scope
Calculate the final CPI
Archive project documents and update the lessons learned repository
Conduct the kick-off meeting
Perform qualitative risk analysis