PMP · Question 18 · Task 11: Plan and manage procurement
A project manager is conducting a procurement for a complex software component. The requirements are not fully defined and will likely evolve. Which contract type is MOST appropriate to share risk and allow for flexibility?
Answer options:
Firm Fixed Price (FFP)
Cost Plus Fixed Fee (CPFF)
Time and Materials (T&M) with a Not-To-Exceed cap
Fixed Price Incentive Fee (FPIF)