For IndividualsFor Educators
ExpertMinds LogoExpertMinds
ExpertMinds

Ace your certifications with Practice Exams and AI assistance.

  • Browse Exams
  • For Educators
  • Blog
  • Privacy Policy
  • Terms of Service
  • Cookie Policy
  • Support
  • AWS SAA Exam Prep
  • PMI PMP Exam Prep
  • CPA Exam Prep
  • GCP PCA Exam Prep

© 2026 TinyHive Labs. Company number 16262776.

    PracticePMI PMP®PMI PMP Practice ExamQuestion 21
    Hard1 markMultiple Choice
    Task 10: Manage project changesProcessChange Management

    PMP · Question 21 · Task 10: Manage project changes

    A stakeholder requests a change to the project scope. The project manager checks the change management plan and sees that the project is in the execution phase. What is the FIRST step the project manager should take?

    Answer options:

    A.

    Deny the request because the scope is baselined.

    B.

    Implement the change if it adds value.

    C.

    Evaluate the impact of the change on all project constraints (cost, schedule, risk, quality).

    D.

    Ask the sponsor for approval.

    How to approach this question

    Change Request Flow: Request -> Assess Impact -> CCB -> Decision.

    Full Answer

    C.Evaluate the impact of the change on all project constraints (cost, schedule, risk, quality).✓ Correct
    Task 10 (Manage Changes) requires a structured approach. Impact analysis provides the data needed for the Change Control Board to make a decision.

    Common mistakes

    Skipping the assessment step.
    Question 20All questionsQuestion 22

    Practice the full PMI PMP Practice Exam

    114 questions · hints · full answers · grading

    Sign up freeTake the exam

    More questions from this exam

    Q01During a daily standup in a hybrid project, two senior developers begin arguing about the archite...HardQ02A project manager takes over a project where the team is demoralized. The previous PM was authori...HardQ03A key stakeholder is unhappy with the product increment delivered in the last sprint, claiming it...HardQ04A project team in a matrix organization is struggling. The functional manager keeps pulling key r...HardQ05A project manager is leading a virtual team spread across four time zones. Team members report fe...Hard
    View all 114 questions →