Medium1 markMultiple Choice

PMP · Question 107 · Task 5: Plan and manage budget and resources

A project manager is leading a project to build a new bridge. The project is using a predictive lifecycle. The PM wants to ensure that the project is on budget. The PM calculates the Estimate at Completion (EAC). The EAC is $1.2M. The BAC is $1M. What does this mean?

Answer options:

A.

The project will finish under budget.

B.

The project is projected to finish over budget by $200k.

C.

The project is ahead of schedule.

D.

The project is finished.

How to approach this question

EAC > BAC = Bad.

Full Answer

B.The project is projected to finish over budget by $200k.✓ Correct
Task 5 (Budget). EAC is the forecast. If it's higher than the budget (BAC), you have a variance at completion (VAC).

Common mistakes

Confusing EAC (Forecast) with AC (Spent so far).

Practice the full PMI PMP Practice Exam

114 questions · hints · full answers · grading

More questions from this exam