PMP · Question 107 · Task 5: Plan and manage budget and resources
A project manager is leading a project to build a new bridge. The project is using a predictive lifecycle. The PM wants to ensure that the project is on budget. The PM calculates the Estimate at Completion (EAC). The EAC is $1.2M. The BAC is $1M. What does this mean?
A project manager is leading a project to build a new bridge. The project is using a predictive lifecycle. The PM wants to ensure that the project is on budget. The PM calculates the Estimate at Completion (EAC). The EAC is $1.2M. The BAC is $1M. What does this mean?
Answer options:
A.
The project will finish under budget.
B.
The project is projected to finish over budget by $200k.
C.
The project is ahead of schedule.
D.
The project is finished.
How to approach this question
EAC > BAC = Bad.
Full Answer
B.The project is projected to finish over budget by $200k.✓ Correct
Task 5 (Budget). EAC is the forecast. If it's higher than the budget (BAC), you have a variance at completion (VAC).
Common mistakes
Confusing EAC (Forecast) with AC (Spent so far).
Practice the full PMI PMP Practice Exam
114 questions · hints · full answers · grading
More questions from this exam
Q01During a daily standup in a hybrid project, two senior developers begin arguing about the archite...HardQ02A project manager takes over a project where the team is demoralized. The previous PM was authori...HardQ03A key stakeholder is unhappy with the product increment delivered in the last sprint, claiming it...HardQ04A project team in a matrix organization is struggling. The functional manager keeps pulling key r...HardQ05A project manager is leading a virtual team spread across four time zones. Team members report fe...Hard
Expert