PMP · Question 108 · Task 1: Execute project with urgency

A project manager is leading a project to develop a new software application. The team is using Agile. The PM wants to ensure that the team is delivering value. The PM uses 'Minimum Viable Product' (MVP). What is this?

Answer options:

A.

The final product.

B.

The smallest version of the product that can be released to customers to gather feedback and validate hypotheses.

C.

A prototype that is thrown away.

D.

The beta version.

How to approach this question

MVP = Learn.

Full Answer

B.The smallest version of the product that can be released to customers to gather feedback and validate hypotheses.✓ Correct
Task 1 (Value). MVP is a strategy to maximize value by minimizing waste (building the wrong thing). It validates the business case.

Common mistakes

Thinking MVP is 'Version 1.0' (it's often smaller) or 'Crappy Product' (it must be viable).