PMP · Question 106 · Task 4: Empower team members
A project manager is leading a project to develop a new software application. The team is using Agile. The PM wants to ensure that the team is self-organizing. What should the PM do?
Answer options:
Assign tasks to team members.
Provide the vision and boundaries (Goal/Constraints), then step back and let the team decide 'How' to do the work.
Leave the team completely alone.
Appoint a team lead to assign tasks.