Medium1 markMultiple Choice
PMP · Question 105 · Task 1: Plan and manage project compliance
A project manager is leading a project to build a new bridge. The project is using a predictive lifecycle. The PM wants to ensure that the project is safe. The PM conducts a 'Safety Audit'. What is this?
A project manager is leading a project to build a new bridge. The project is using a predictive lifecycle. The PM wants to ensure that the project is safe. The PM conducts a 'Safety Audit'. What is this?
Answer options:
A.
A plan to be safe.
B.
A structured, independent review to determine whether project activities comply with organizational and project policies, processes, and procedures.
C.
A check of the product.
D.
A risk analysis.
How to approach this question
Audit = Process Check.
Full Answer
B.A structured, independent review to determine whether project activities comply with organizational and project policies, processes, and procedures.✓ Correct
Task 1 (Compliance) and Task 7 (Quality). Audits check the *process* (Quality Assurance), while Inspections check the *product* (Quality Control).
Common mistakes
Confusing Audit (Process) with Inspection (Product).
Practice the full PMI PMP Practice Exam
114 questions · hints · full answers · grading
More questions from this exam
Q01During a daily standup in a hybrid project, two senior developers begin arguing about the archite...HardQ02A project manager takes over a project where the team is demoralized. The previous PM was authori...HardQ03A key stakeholder is unhappy with the product increment delivered in the last sprint, claiming it...HardQ04A project team in a matrix organization is struggling. The functional manager keeps pulling key r...HardQ05A project manager is leading a virtual team spread across four time zones. Team members report fe...Hard
Expert