Medium1 markMultiple Choice
Task 1: Plan and manage project complianceBusiness EnvironmentComplianceQuality

PMP · Question 105 · Task 1: Plan and manage project compliance

A project manager is leading a project to build a new bridge. The project is using a predictive lifecycle. The PM wants to ensure that the project is safe. The PM conducts a 'Safety Audit'. What is this?

Answer options:

A.

A plan to be safe.

B.

A structured, independent review to determine whether project activities comply with organizational and project policies, processes, and procedures.

C.

A check of the product.

D.

A risk analysis.

How to approach this question

Audit = Process Check.

Full Answer

B.A structured, independent review to determine whether project activities comply with organizational and project policies, processes, and procedures.✓ Correct
Task 1 (Compliance) and Task 7 (Quality). Audits check the *process* (Quality Assurance), while Inspections check the *product* (Quality Control).