PMP · Question 26 · Task 12: Manage project artifacts
A project manager discovers that project artifacts are stored in multiple locations with different version control systems, and team members are sometimes working with outdated information. This has led to rework and confusion. What should the project manager do FIRST?
Answer options:
Establish a centralized repository with clear version control and access procedures
Send an email to all team members about the importance of using current versions
Assign a team member to manually check that everyone has current versions
Schedule weekly meetings to review which artifacts have been updated