Hard1 markMultiple Choice
Task 1: Execute project with the urgency required to deliver business valuebusiness valueMVPscope managementstakeholder involvement

PMP · Question 15 · Task 1: Execute project with the urgency required to deliver business value

A software development project has an opportunity to deliver a minimum viable product (MVP) three months ahead of the original schedule, which could capture significant market advantage. However, this would require descoping some planned features. What should the project manager do FIRST?

Answer options:

A.

Proceed with the MVP delivery since early market entry provides competitive advantage

B.

Analyze the business value of early delivery versus the value of the descoped features with key stakeholders

C.

Maintain the original scope and schedule to ensure all planned features are delivered

D.

Ask the development team to work overtime to deliver all features on the accelerated timeline

How to approach this question

Look for approaches that focus on business value analysis and stakeholder involvement in value-based decisions.

Full Answer

B.Analyze the business value of early delivery versus the value of the descoped features with key stakeholders✓ Correct
Delivering business value requires analyzing trade-offs between early delivery and feature completeness, involving stakeholders in value-based decision making.

Common mistakes

Making unilateral decisions about scope changes, or rigidly adhering to original plans without considering value opportunities.

Practice the full PMI PMP Practice Exam 6

100 questions · hints · full answers · grading

More questions from this exam