    PracticePMI PMP®PMI PMP Practice Exam 5Question 81
    Hard1 markMultiple Choice
    Task 9: Collaborate with stakeholdersstakeholder collaborationcompeting prioritiesbusiness objectivesstakeholder alignment

    PMP · Question 81 · Task 9: Collaborate with stakeholders

    A project manager is working with stakeholders who have conflicting priorities for a new enterprise system. The finance team wants cost reduction features, the operations team wants process automation capabilities, and the sales team wants customer-facing enhancements. Each group believes their priorities are most critical for business success. What should the project manager do FIRST?

    Answer options:

    A.

    Facilitate a collaborative session to understand each group's underlying business objectives and identify alignment opportunities

    B.

    Ask the sponsor to prioritize the competing stakeholder requirements based on strategic importance

    C.

    Develop a phased implementation approach to address each stakeholder group's priorities in sequence

    D.

    Create separate project workstreams to address each stakeholder group's priorities independently

    How to approach this question

    When stakeholders have competing priorities, facilitate collaborative understanding of underlying objectives to find alignment opportunities rather than having others decide or separating the work.

    Full Answer

    A.Facilitate a collaborative session to understand each group's underlying business objectives and identify alignment opportunities✓ Correct
    Stakeholder collaboration requires understanding underlying business objectives rather than just stated requirements. This often reveals alignment opportunities and enables more effective priority setting.

    Common mistakes

    Students often choose sponsor decision-making (B) or structural solutions (C or D), missing the opportunity for collaborative stakeholder alignment around business objectives.
    Question 80All questionsQuestion 82

    Practice the full PMI PMP Practice Exam 5

    94 questions · hints · full answers · grading

    Sign up freeTake the exam

    More questions from this exam

    Q01During a sprint retrospective in an agile project, two senior developers engage in a heated argum...HardQ02A project manager is leading a hybrid software development project where the client has clearly d...HardQ03A project manager notices that a high-performing team member has become withdrawn over the past t...HardQ04During iteration planning for a hybrid software project, the team identifies a new technical risk...HardQ05A project has the following earned value metrics at the end of Month 6:<br/>- Budget at Completio...Hard
    View all 94 questions →