PMP · Question 82 · Task 10: Build shared understanding
During a project planning session, different stakeholders express conflicting interpretations of a key project deliverable. The technical team understands it as a data integration platform, the business team expects a complete analytics solution, and the end users anticipate a self-service reporting tool. What should the project manager do FIRST?
Answer options:
Update the project charter to provide clearer deliverable definitions
Ask the sponsor to clarify which interpretation is correct for the project
Facilitate a requirements clarification session with all stakeholders to reach consensus on the deliverable
Proceed with the technical team's interpretation since they will be implementing the solution
94 questions · hints · full answers · grading