Hard1 markMultiple Choice
Task 16: Ensure knowledge transfer for project continuityknowledge transferoperations transitionoperational readinesscapability building

PMP · Question 66 · Task 16: Ensure knowledge transfer for project continuity

A project manager is preparing for the transition of a complex e-commerce platform from the development team to the operations and support teams. The operations team has limited experience with the new technology stack and microservices architecture. The development team has focused on feature delivery and has not created comprehensive operational documentation or troubleshooting guides. What should the project manager do FIRST?

Answer options:

A.

Schedule comprehensive training sessions for the operations team on the new technology stack and architecture

B.

Extend the development team's involvement to provide ongoing operational support during the transition period

C.

Conduct a comprehensive knowledge transfer assessment to identify operational knowledge gaps and develop a structured transfer plan

D.

Create detailed operational documentation and troubleshooting procedures for all system components

How to approach this question

Look for systematic approaches that assess operational knowledge gaps and develop comprehensive transfer plans based on operations team needs.

Full Answer

C.Conduct a comprehensive knowledge transfer assessment to identify operational knowledge gaps and develop a structured transfer plan✓ Correct
Effective knowledge transfer for operations requires systematic assessment of existing operational knowledge, identification of gaps, and understanding of operations team needs to develop comprehensive transfer plans.

Common mistakes

Students often choose training or documentation approaches rather than recognizing the need to assess operational knowledge gaps and transfer requirements first.